BRIEF: INSTALLATION OF MACHINERY AT WORKSHOP NO. 5 AT HIGHER INSTITUTE FOR PLASTICS, RIYADH SAUDI ARABIA. INSTALLATION WORKS, INCLUDED INSTALLATION OF VERY HIGHLY SOPHISTICATED AND MODERN MACHINERY, WHICH WAS IMPORTED BY THE OWNER OF THE PROJECT, “TECHNICAL & VACATIONAL TRAINING CORPORATION”. THE WORKS INCLUDED DOWNLOAD THE MACHINERY FROM THE CONTAINERS, WITH SPECIALIZED TECHNICAL EXPERTS, WITHOUT DAMAGING THE MACHINES, AND TRANSPORTING THE VERY HEAVY AND HUGE MACHINES, INSIDE THE WORKSHOP, MAKING ELECTRICAL AND CALBE NETWORK, AIR COMPRESSED NETWORK AND COLD WATER PIPING NETWORK, SPECIAL FOUNDATIONS, DRAINAGE CHANNELS ETC FOR THESE SPECIALLY IMPORTED MACHINES. |